Planning to submit application for building permit for a 2nd of 2 buildings of a small (8,100 sf each) climate controlled facility, I am within the city limits and subject to the 2015 International Building Code, my initial plans included the 2nd building on the site plan, but did not include electrical nor HVAC for building 2, the site is completely finished and currently in operation (all driveways, foundations, driveways, parking, hydrants are in place) save for the 2nd building which will only require electrical (lighting) and Hvac in order to be operational. Seeking feedback / advice on how best to approach this in an effort to be exempt from paying "again" architect and MEP...Our city is currently using "3rd party verification" since they lack staff...My initial plan is to re-submit initial site plan and have a draftsman do electrical and HVAC plans...If anyone can share a draftsman contact I appreciate it.
Thank you in advance
------------------------------